Stourflex were engaged to provide a thermal expansion solution for a prestigious project that presented an exceptionally demanding set of engineering and structural design challenges. During the design stage, concerns were raised by WML Consulting, the project structural engineers, regarding the forces generated by the proposed high-pressure steam system and the potential impact these loads could have on the existing structure.
Both the main consultant, Jacobs, and WML Consulting required detailed assurances that the anchor forces generated by the thermal expansion system could be safely contained without adversely affecting the existing brickwork, concrete floors and structural walls. Given the age and nature of the structure, it was essential that the expansion design balanced the operational requirements of the steam system with the limitations of the existing building fabric.
Working closely with the consultants and project team, Stourflex developed a bespoke expansion design that accommodated the requirements of the Logstor pre-insulated pipework system while addressing the structural concerns identified during the design process. Detailed engineering calculations were produced to quantify the forces generated by the thermal expansion system and demonstrate how these loads would be controlled and safely contained throughout the installation.
To further reduce the structural loads imposed on the building, Stourflex introduced Sikla to the project to provide an advanced pipe support solution for both the underground pipework and the existing service trenches. By utilising Sikla’s Simotec Ultraglide pipe shoes, supplied by Stourflex as the JP155 range, mounted on engineered siFramo support frames, friction within the system was significantly reduced. This approach substantially lowered the anchor forces that would otherwise have been generated using conventional pipe support methods, providing a more efficient and structurally sympathetic solution.
Through close collaboration with Jacobs, WML Consulting and the wider project team, Stourflex were able to deliver a robust expansion design that satisfied the operational requirements of the high-pressure steam system while providing the consultants with the confidence that the existing structure would remain protected.
Stourflex were proud to contribute to a project that required such a high level of technical engineering and coordination. The successful delivery of a solution that balanced thermal expansion requirements with complex structural constraints demonstrates the value of early collaboration and specialist engineering expertise.
Talk to our experts about your project, completely obligation-free.
We use cookies to improve your experience on our site. By using our site, you consent to cookies.
Manage your cookie preferences below:
Essential cookies enable basic functions and are necessary for the proper function of the website.
Statistics cookies collect information anonymously. This information helps us understand how visitors use our website.
Vimeo is a video hosting platform for high-quality content, ideal for creators and businesses to showcase their work.
Service URL: vimeo.com (opens in a new window)